Most of the short-term project elements are associated with the extension of the runways, the provision of the runway safety areas, and the ancillary projects that would enable the runway extensions to occur. These projects are proposed to begin in summer 2013. The projects will be completed in two phases. It is anticipated the runway extension may be completed by fall 2014.